Functions of Production Version

Can somebody enlighten me on the functions of production version and some tips on its configuration?

Production Versions are used to describe the production process to be used for planned / production order.

You can use the production versions based on:
1. Lot size qty
2. Bom explosion dates
3. Based on MRP Group

Why is it required?

Suppose you have 2/3 production lines and 2/3 alternative BOMs to produce one FG.

How system will come to know which BOM and Routing to be used. This is done thru Prod.Version.

In production version we maintain the combination of BOM and routing.
Also it can be designed with lot size or validity period.
Go to MM02--->MRP4 / Work scheduling view ----> Prod.Version.
Enter the validity period and lot size.
After entering the reqd. routing no. and BOM alternative , carry a check.
After getting the Green signals ,Continue.
Thus you have saved the prod. version.
Mass processing TCode- C223.

Does this mean that I have to activate all the BOM’s if in case I have 3 alternative BOM’s? if yes, then, will it these 3 BOM’s be exploded in MRP? I’m just worried ‘coz I might bloat our inventory if there are three active BOM’s.

No.First of all need not worry about the BOM explosion.

As I told you earlier which BOM and which Routing is decided by Prod.Version.

So in MRP the active prod.version only will be considered. Thus active BOM and active Routing will be used for MRP.

The question comes:  How to deactivate the alternative BOMs and Routing?

Two Ways:
1. You lock all other non-relevant Prod.Versions in MM02 of the FG/SFG material.(Every alternative BOM and routing forms a Prod.Version) Thus even if there are 2/3 prod.versions System will go and check for Unlocked prod. version and use it.

2. If you don't want to do this business of "Lock & Unlock" just place the required version at the first place in list of prod.versions in MRP4 view of the material.
Once system finds the first prod.version it will not spend energy in searching other alternatives.

Also please.don't forget to maintain the selection value of  "2" in MRP 4 view for BOM selection.

This will enable you to start the use of prod. version functionality in SAP-PP.(very good tool for practical purposes, costing and MRP).                                                                                                      *--  : Praveen

Plan Strategy
Planning Strategy Selection

Get help for your SAP PP Problems
Do you have a SAP PP Question?

SAP PP Books
SAP Production Planning and Control Certification, Interview Questions and Configuration Reference Books

SAP PP Tips
SAP PP Tips and Production Planning/Control Discussion Forum

Best regards,
SAP Basis, ABAP Programming and Other IMG Stuff
http://www.erpgreat.com

All the site contents are Copyright © www.erpgreat.com and the content authors. All rights reserved.
All product names are trademarks of their respective companies.  The site www.erpgreat.com is in no way affiliated with SAP AG.
Every effort is made to ensure the content integrity.  Information used on this site is at your own risk.
 The content on this site may not be reproduced or redistributed without the express written permission of
www.erpgreat.com or the content authors.