Bills Of Material
Q: We have a BOM -
'A' with two packing materials 'X' and 'Y'. For 1000 units of 'A', 1 packing
material of 'X' is required and for 50 units of 'A', 1 packing material
of 'Y' is required. Base quantity of 'A' is
defined as 1000. How can I define 'X' & 'Y' or in fact 'A'?
A: Make the base quantity of 'A' as 5000. The resulting
component quantities would be 5 of 'X' and 100 of 'Y'.
Work Centers
Q: Can we have more
than 6 standard values in standard value key?
A: One
way to achieve this is to create another operation step using the same
work center. However this shall be with a control key that is not a milestone.
When the milestone operation is confirmed, the previous operations up to
the next milestone are automatically confirmed. To get the desired number
of standard values , all the 'non milestone' steps can be built depending
on the need.
Routing
Q: Can we use same
routing for materials undergoing the same process/operations? Can we avoid
separate routing for each and every material produced?
A1: Presume that there
are 50 products and the fabrication shop uses a set of 10 machines. If
all these products use the same settings of the machines, Reference Operation
Sets (task list type S) can be setup for common processes that use the
same work centers. However costing, scheduling and capacity will be affected
if each product has different setup time and Reference Operation sets can
not be used.
A routing for each material number ( type N or R) has
to be set up and within that routing, the Reference Operation Set can be
used.
However you can by try utilizing the KMAT material and
product variants invariant configuration to avoid separate routing for
each material.
A2: You may create a routing group. Go into routing
creation and enter the plant and the group name. If you want you may name
the group , else name is assigned by internal counter). Create the routing
with the work centers, operation times, etc. Go to the "Header overview"
screen and click on the "Mat Alloc" screen. Fill in the blanks with all
the material masters that use this routing.
Q: Scheduling times
can be defined in the material master record by;
# entering the in-house production time. This value can
be updated from the routing by the system.
# entering the setup, tear down, processing, and interoperation
times. If these values are maintained, the system determines the in-house
production time on the basis of lot size.
How do you get the system to update
this
value from the routing?
A: In routing, carry out scheduling. Go into the
routing operation overview and follow Extras -> Scheduling -> Results.
The pop-up window displays the scheduling data. At the bottom there is
a pushbutton to copy the scheduling data to the material master Check this
push button to update master data.
Q: We have deleted a group key in an operation
in routing and the same does not appear for this routing (CA02). But we
noticed that entries are maintained in table PLPO and the deletion indicator
is not set. How does the system remember this deletion
of group key?
A: You may look at the tables PLKO, MAPL and PLAS.
Sales & Operations
Planning
Q: We defined SOP
in months. However during SOP
transfer to demand management, our independent requirements are
appearing in weeks. How can we correct this from weeks
into months ?
A: Check transaction
OMPA for general split. OMPS - based on the MRP group. Ensure that MRP
group assigned to the material. Delete any allocations in these tables.
Then periods will be transferred to Demand Management with the same splits
as in SOP. Also check whether the value of period
is set as "month" at your plant level in Transaction 'OMP7'
Demand Management
Q: Sales quantities
in SOP for certain days are transferred into Demand Management and are
shown as planned independent requirements. We need to keep the settings
in SOP and change the periods in Demand Management?
We would like to have a rolling horizon, for
ex: the following 4 weeks on a daily basis, after that on a monthly basis.
What is the best way to do this?
A: Use
the automatic period split function.
M R P
Q: We have a lot size
procedure here which is creating more order proposals. How do you set the
limit
value for maximum number of MRP
order proposals per date in IMG?
A: Under customization,
try materials management->consumption based planning->maintain all plants
Q: What is the difference
between "planned consumption" and "Unplanned consumption"?
Can safety stock calculation be done on either of these?
A: While customizing movement
types (OMJJ) it is defined as to which set of consumption values gets posted
during the material movement. For some it may always be the total consumption
and for some it is always the unplanned one and for some it is dependent
on whether the issues were done with reference to a reservation ie., a
planned consumption. The way these consumption values are taken into account
in MRP is defined in the customizing of MRP types.
For Reorder point planning (VM)
the total consumption is used to calculate the safety stock and the reorder
point.
For Forecast based planning (VV)
the total consumption is used to build the forecast which will be used
to compile the order proposals.
For Deterministic MRP (PD) the
unplanned consumption is used to calculate the forecast which in turn is
added to the actual demand.
Q: We want the system to run a single level MRP
automatically on receipt of sales order. How to configure triggering event
based MRP?
A: This can only be run if material master has
planning strategy 41 (made-to-order) in the MRP2 view. We need to run for
other MRP types. We have to create a user exit in the sales order processing
(VA01) to start MRP based on data from our sales transaction.
Q: We have an assembly 'A' using a subassembly
'B'. 'B' in turn uses raw material 'C'. Item 'A' is an MPS and is duly
marked in Material Master. Item 'B' and 'C' are marked as 'PD'. When demand
for 'A' is entered and MPS is run , upto which level the requirements are
taken care of?
A: MRP can be run depending on your requirement.
For example:
-
Single Item / Single Level from MPS - Transaction Code MD42
- Only the top MPS item ( 'A' in this case) is planned and dependent requirements
will be passed to MRP item ( 'B' ) . Run MRP, Transaction MD02 on 'B' to
plan it and all MRP items below .
-
Single Item / Multi Level from MPS - Transaction Code MD41
- All levels are planned - A , B & C
-
Total Planning from MPS online or background - Transaction
Code MD40 or MDBS
Without marking the checkbox " Process MRP materials"
is like case ( 1) above and with the checkbox marked is like case (2 ).
Production Orders
Q: We get an
error
message "Control parameters for scheduling not defined" while creating
test production Orders. Why?
A: Before you attempt
creating Production orders, configure your
Order types- Transaction Code OPHJ
Order type Dependent parameters - Transaction Code OPL8
Backorder Scheduling - Transaction Code OMIH
Scheduling Levels - Transaction Code OMIF
Q: We
are trying to create Purchase Requisition from MRP run. We have material
, info Record, Source list , Demand in place. MRP
is always creating plan order. Why?
A: Check
the procurement type in MRP view of material master. Check 'Create Purchase
requisition' indicator while running MRP. If you want purchase requisitions
to be created in the opening period, select the for MRP control parameter
'create purchase requisitions' as '1'.
Q: what
is the option "Documented goods movements"
on Selection of Individual Object Lists (transaction code CO28)?
A: Use Transaction
code OPL8 to customize by choosing the order type, select all the checkbox
under "Documentation of goods movements" at the bottom of the page. Create
a new Production order, make GI to it, and run the report.
Q: We would like to have
a report/inquiry that would indicate variances
(materials, material quantities) between material recipe and actual process
orders. We tried ME2M but this gives us a list of purchasing documents
and not the consumption deviation. Where can I get such consumption
deviation (master recipe Vs. Process> Orders)?
A: Do a data collection first.
Menu Path - Accounting->Controlling->Product cost acctg->Process
mfg->Information system->Cost object hierarchy->data collection
(If you are using order hierarchy you would select order
hierarchy in place of cost object hierarchy in the menu path.)
Then,
Accounting->Controlling->Product Cost Accounting->Order
Related Production->Information System
Choose Report Period Costing - Target/Actual production
variance
Q: We have two components ( 'X' & 'Y' ) in
a production order in a process oriented production process. When 50 numbers
of component 'X' are issued, we need the system to automatically issue
100 numbers of component 'Y' based on ratio of 1
to 2. Where do I specify these ratios?
A: You can define the ratio in BOM and material
may be issued with reference to BOM.
Q: We have two storage locations are '0001' and
'0600'. Default storage location in Process
order is always '0001' What determines this default location?
A: Look into OSS notes: 100757, 63493, 96262,
87843, 82033, 64946.
The Storage location as configured in the Supply area
has the highest priority.
Q: We
need to do GI of components to production order using Back-flush. The component
stock is managed in Batches. The Batch to be back-flushed
is selected by FIFO from the issue storage location. How can we set this
up?
A: With the following settings, the batches are
selected the moment the production order is released.
1: Set up batch determination the way that the batches
in batch selection are sorted the right way. e.g. sorted by expiry date
2: Use automatic batch selection in disp view.
3: Ensure that the components are allowed to be back-flushed
(material master / work center)
Q: We want to report on several
status combinations like each order that has status 'Not deleted'
and 'Not technically completed'. What set up is required?
A: Check transaction CO28. In the selection screen
note the possible selection 'System Status' . You can select TECO for technically
complete an DLT for deleted from the list. Select the Excl. indicator also.
You may also try transaction CO26 (Logistics -> Production
-> Production control -> Control -> Information systems -> Order Info System
-> Object overview). Before executing the transaction report, combinations
of statuses can be selected or exclude them.
Q: How can we
shut off the "automatic costing indicator" and the
"automatic scheduling indicator" which go on when the production
order is released?
A: For "no
automatic costing" follow the IMG path
Production -> Production orders ->Master data -> Order
- >Define order type dependent parameters
Select the order type for which u automatic costing is
not required. In the controlling settings, select "no automatic costing"
For "no automatic scheduling" , follow the IMG path :
Production ->Operations - >Scheduling -> Define control
parameters
Select the order type and go to details. Deselect " automatic
dates "
Alternatively, you can find indicators in the control
key, which is in the routing. Transaction OPL8 gives you costing indicators
(Order type dependent parameters), and OPJU (control table for scheduling)
gives some scheduling options.
Variable Size
Q: How can I use variable
size items?
A: For example, consider an item A with 'kg' as
base Unit Of Measurement(UOM) and 'm3' as stock keeping/issue unit. Conversion
factor is 1kg = 2.4 m3.
In the BOM of 'B' ,number of A required are specified
(say 5).
Specify the 3 variable dimensions i.e. length, width
& thickness- say 2000mm X 3000mm X 4mm = 0.024 m3
As per BOM - 'B' , the quantity of A required is 0.024
X 5 = 0.120 m3
If a production Order is released for 15 numbers of 'B'
, the quantity of variable size unit will be 1.20 m3.
You can change the length, width or thickness in the
production order & check the resulting variable size item quantity.
At the same time this requirement can be seen in 'kg' in stock/requirement
list.
Others
Q: How to configure
the planning calendar for the ATP calculation where goods
are shipped every other working day?
A: Use Transaction MD25 and define calculation
rule for every other working day. Check the lot size settings in OMI4 and
maintain relevant data in MMR.
Q: We have two different production lines with
different operations. One production line works 5 days a week and the other
7 days a week. The factory calendar is assigned to the plant for 5 days
a week. This calendar is checked when MRP is run. How can we assign
5 day a week and 7 days a week against a factory
calendar to the related resources? Is it possible to have two types
of calendars?
A: Assign factory calendars to the work centers.
Q: What is the difference
between by-product and co-product and how do you
differentiate
them in a BOM?
A: In case of Co-product costs are settled with
a apportionment structure. In case of By-product the price of this by-product
is credited to the order or the material stock account of the lead material
being manufactured. Co-Product as well as by-product are defined as BOM
Components/Items. Both of them have negative quantities. ( Not all negative
quantity items fall under these categories!). When BOM is created for FERT
, you can see one indicator in COMPONENT DETAILS screen for co-product.
You need to define the co-products with this special indicator .
Q: What are some important
tables used in PP ?
A: For orders:
CUAFVD dialog structure for order headers and items
AFPO - Order item
AFFLD Order: Dialog table for order sequences (AFFL)
MOPER Operation for production order
KBED Capacity requirements
AFRU Order completion confirmations
RESB Reservation/Dependent Requirements
AFFHD Structure of PRT's in orders
SOPER Sub-operations
SAFRU Sub-operation confirmations
SKBED Capacity requirements for sub-operation
MRP table is MDTB.
For PI:
CAUFV - AFVC Operation within an order
AFFT Order Process Instructions
AFFV Order process instruction values
Some other tables of interest:
PLKO, MAPL , PLAS.
PP Flow
The
Overall Flow For SAP PP
Get help for your SAP PP Problems
Do you have a
SAP PP Question?
SAP PP Books
SAP Production
Planning and Control Certification, Interview Questions and Configuration
Reference Books
SAP PP Tips
SAP PP Tips and
Production Planning/Control Discussion Forum
Best regards,
SAP Basis, ABAP Programming and Other IMG Stuff
http://www.erpgreat.com
All the site contents are Copyright © www.erpgreat.com
and the content authors. All rights reserved.
All product names are trademarks of their respective
companies. The site www.erpgreat.com is in no way affiliated with
SAP AG.
Every effort is made to ensure the content integrity.
Information used on this site is at your own risk.
The content on this site may not be reproduced
or redistributed without the express written permission of
www.erpgreat.com or the content authors.
|