PP/DS Heuristic Question
When executing a PP/DS Heuristic we want to plan only
a certain amount of products. In the selection criteria of the Production
Planning Run (background processing) we cannot enter the restrictions which
lead to the desired scope of products to be planned (Propagation Range,
Object 'Products' are not sufficient). Somehow we want to base the selection
of
In our Heuristic run no PPM explosion takes place, only externally procured products are planned. Does anybody know a solution for this selection issue?
You will need to set the object type for selection to 5 - Copy objects from customer exit APOCDPS1 This will allow you to use the customer exit to select the objects you require via ABAP.
Part number strategy As we consider moving to R/3 globally and then implement
APO we are struggling with part numbering strategy. Without APO in
place is there a way to allow different countries (different company and
plant in our case) to maintain unique part numbers and still accomplish
inter-company stock transfers? Or do we need APO for this and, therefore,
need to force a
I do not know how you can accomplish this w/o APO, although
you may be able to.
With APO each R/3 instance can use the same part number
aslong as each uses its own Business System Group. You will
need to modify CIF a little, but it should work.
In KC we have a unique part number trough Latin America
for finished products, semielaborated and raw materials. Implement
this is very hard because you need a team of master data that all countries
because first you have to prepare all the codes that you go to upload,
then you have to standarize the codes with a unique part number.
For us is useful overall in