Guideline to upgrade from 3.1
to 4.6 with HW upgrade at the same time
1. Do a system copy of the 3.1 instance to the new box. 2. Bring up 3.1 instance in new box. 3. Upgrade the Development/Staging instance and resolve all errors and issues. Create SPAU/SPDD modifications, if any. 4. Timing the upgrade processes - to determine how
long the whole processes take.
5. Do a system copy of the 3.1 instance to the new box again 6. Bring up 3.1 instance in new box. 7. Make the 3.1 instance in new box as the Production instance. 8. Make the 3.1 instance in the old box as the Development/Staging
instance or a standby Production Box in case
9. Upgrade the Production instance as planned (i.e. 3 full working days). 10. Acceptance testing.
Questions
Best regards,
All the site contents are Copyright © www.erpgreat.com
and the content authors. All rights reserved.
|