How can I copy users created in development to production?
1. Login to the client in your DEV system from where you want to copy. 2. Execute SCC8.
3. Specify the background server name i.e. the server name where your DEV system is available. 4. Click on 'schedule job' button.
5. You will have options to specify the start time.
6. Login to the destination client and execute SCC6.
7. Specify the target client and click on 'Import'.
Additional: Can we do a copy of sap_user from SAP version 4.6C to ECC 6.0? The answer is : NO You can find the answer in the SAP note. Note 552711 - FAQ: Client copy Point 4.
Notes: Options when you do a client export / import or local client copy. SAP_UCSV Customizing, User Master Records and User Variants. SAP_UCUS Customizing and User Master Records. SAP_UONL User Without Authorization Profiles and Roles. SAP_USER User Master Records and Authorization Profiles. If you are just looking for only the user master records then you just can use SAP_UCUS. |
|
See Also
SAP Basis Admin Books
SAP Basis Tips
Administration In SAP - Sapgui, Unix, SAP ITS, Router, Client Copy and IDES Main Index
All the site contents are Copyright © www.erpgreat.com
and the content authors. All rights reserved.
|