SAP S4 HANA Production and Manufacturing Certification

"SAP S4 HANA Production and Manufacturing Certification

These questions are similar to those asked in the actual test. How should I know? I know because, although I have been working as an SAP HANA & SAP PP Consultant for many years, I have recently certified myself with the latest version of the Associate Certification test.

Before you start, here are some key features of the SAP Certified Application Associate - SAP S/4 HANA Production Planning and Manufacturing Exam:

  • This certification exam verifies that the candidate has the knowledge required in the area of SAP S/4 HANA Production Planning and Manufacturing.
  • This certificate builds on the basic knowledge gained through related SAP HANA and SAP Production Planning and Manufacturing training and is preferably refined by practical experience within an SAP HANA Production Planning and Manufacturing project team, whereby the consultant applies acquired knowledge in this specialist area practically in projects.
The exam is computer-based, and you have three hours to answer 80 questions. The questions are mostly multiple-choice type, and there is no penalty for an incorrect answer. Some questions have more than one correct answer. You must get all the options correct to be awarded points. For questions with a single answer, the answers will have a button next to them. You will be able to select only one button. For questions with multiple answers, the answers will have a tick box next to them, allowing you to select multiple answers.

You are not allowed to use any reference materials during the certification test (no access to online documentation or any SAP system).

Clearing the certification will not automatically lead you to a job. However, a certification with some project experience will certainly open many doors for you. So, if you have little or no experience, you should get yourself certified, gain some project experience, and then the whole SAP world will be open for you to explore.

Helping you with the first step on your ladder to success is this book! Some unique features of this book include:

  • There is no other material in the market for the SAP Certified Application Associate - SAP S/4 HANA Production Planning and Manufacturing exam.
  • The authors have themselves cleared the exam.
  • All questions are in multiple-choice format, similar to the questions you will get in the actual exam.
  • Over 125 authentic questions test the exact same concepts that will be tested in your exam!
Sample Questions and Answers

1) Material requirement planning is completed, and the system uses the planned order for external procurement quantity. Then, into which of the following will the order be converted?
(There are two answers to the question)

(a) Production order
(b) Sales order
(c) Purchase order
(d) Purchase requisition

Answer: c, d

Explanation:

Within-house, the system creates planned orders for planning the production quantities. When planning is complete, planned orders can be converted into production orders.

With external procurement, the system either uses a planned order or uses a purchase requisition directly to plan the external procurement quantity. When planning is complete, the order is converted into a purchase requisition, which is subsequently converted to a purchase order.
Using the creation indicator for purchase requisitions on the initial screen of the planning run, you control whether the system immediately creates purchase requisitions directly or first creates planned orders.

2) Which of the following internal planning elements can be changed, rescheduled, or deleted at almost any time?
(There are two answers to the question)

(a) Planned orders
(b) Material reservations
(c) Dependent requirements
(d) Purchase requisitions

Answer: a, d

Explanation:

Material requirements planning takes current and future sales as its reference point. The planned requirement quantities trigger the MRP calculation. In MRP, the requirements elements include sales orders, planned independent requirements, material reservations, the dependent requirements created by exploding the BOM, and so on.

If the MRP run determines shortage quantities, the system creates proposals: purchase requisitions and planned orders. These are internal planning elements that can be changed, rescheduled, or deleted at almost any time.

3) You are trying to make an entry in the planning file for a material, but the system is not giving you the option to do that. Which of the following is the reason? 
(Only one answer is correct)

(a) The plant parameters have not been maintained
(b) The MRP views for the material have not been maintained
(c) The material requirement planning for the plant has not been activated
(d) Both a and b

Answer: c

Explanation:

In the Customizing activity "Activate MRP and Set up Planning File", you can specify for which plant an MRP run is to be carried out by activating material requirements planning. You can only make entries in the planning file once this indicator has been set, which means that:

  • When a material that is relevant for MRP is created, the system copies the material number to the planning file and flags it for planning.
  • Whenever a change relevant to MRP is made, the system flags the material for planning.
4) Which level will take priority as the settings for material requirement planning are possible at three levels?
(Only one answer is correct)

(a) Material master
(b) MRP group
(c) Plant parameters
(d) Material number

Answer: a

Explanation:

The settings for material requirements planning are controlled on three levels:

  • Material master (MRP views)
  • MRP group (Customizing step Carry out Overall Maintenance of MRP Groups)
  • Plant parameters (Customizing step Carry out Overall Maintenance of Plant Parameters)
If a setting is possible on several levels, the setting in the material master takes priority over the setting in the MRP group to which the material is assigned. The setting in the MRP group takes priority over the setting in the plant parameters.
 
Key Takeaways or Conclusions

The book provides a thorough and comprehensive overview of SAP's production and manufacturing modules, with a particular emphasis on the latest version of the software, SAP S/4 HANA. It covers a wide range of topics and provides practical guidance on how to use SAP's production and manufacturing modules effectively.

Author's Background and Qualifications

W Ross is an experienced SAP consultant and trainer with over 25 years of experience in the field. He has worked on numerous SAP implementation projects and has extensive knowledge of SAP's production and manufacturing modules.

Target Audience or Intended Readership

The book is intended for SAP consultants, project managers, and business analysts who are involved in the implementation and management of SAP's production and manufacturing modules.

The Book's Biggest Takeaway and Point in a Singular Sentence

The book "SAP S4 HANA Production and Manufacturing Certification" by W Ross is a comprehensive guide that provides practical guidance on how to use SAP's production and manufacturing modules effectively, with a particular emphasis on the latest version of the software, SAP S/4 HANA.

SAP S4 HANA Production and Manufacturing Certification

SAP Books

SAP Production Planning Books
SAP PP Certification, Interview Questions and Configuration Books

SAP PP Tips
SAP PP Tips and Production Planning/Control Discussion Forum

ERPGREAT.com
SAP ERP Modules, Basis, ABAP and Other IMG Stuff

All the site contents are Copyright © www.erpgreat.com and the content authors. All rights reserved.
All product names are trademarks of their respective companies.  The site www.erpgreat.com is in no way affiliated with SAP AG.
Every effort is made to ensure the content integrity.  Information used on this site is at your own risk.
 The content on this site may not be reproduced or redistributed without the express written permission of
www.erpgreat.com or the content authors.