In SAP, there is an option in costing variant, transfer
control option for Standard cost transfer plant to plant.
We have three plants which are manufacturing. Some
of the Semi-Finished Goods (SFG) are used as input material. We already
have run the standard cost
What setting need to be maintain to transfer SCE to other plant? Answer: 1. Go to OMD9 2. Click on New entries: Enter your Plant = Plant 2 (receiver plant) "SP Pr Type" = Z1 and Proc Type = F; 3. Under Special Procurement Section Enter U as special procurement and Plant 1 in the Plant Field (Transferring plant) 4. Save this entry, and in Mat Master of Plant 2, specify F as Proc Type and Z1 as Special proc key 5. Run CK11N in Plant 2 and release from CK24 In the Transfer Control - Maintain the Setting to Transfer Current Cost Estimate in "Cross Plant Scenario". |
|