BOM Is Not Exploding In P.O.

While creating subcontract order, BOM is not exploding in P.O even though we are maintaining BOM for end product.  How to solve this problem?

Please check the following things :

1. In Material master MRP4 view - Field "Individual/Coll" should have value "2" or "Blank" & In BOM (Transaction code CS03) item detail section - Field "Explosion Type" should have value  "LB" ("Individual/Coll" should have value "2" or "Blank") .

2. PIR should have PIR Info category "3" , i.e., Subcontracting PIR must available for header material which we receive back from subcontractor.

3. Special Procurement Key must be "30" in material master MRP2 View.

4. Purchasing Item Category must be "L" and production BOM must be maintained, if you want to explode BOM in PO.

5. Please check BOM valid period is effective from in Tcode cs03 

6. Please check your PO date against the valid date of the BOM valid period.

*-- Gajendra

Fast Links:
Email Purchase Order
External Send - Sending PO by email

Get help for your SAP MM problems
Do you have a SAP MM Question?

SAP Books
SAP Certification, Interview Questions, Functional, Basis Administration and ABAP Programming Reference Books

SAP Material Management Tips
SAP MM Configuration Tips and Materials Management Discussion Forum

Best regards,
SAP Basis, ABAP Programming and Other IMG Stuff
http://www.erpgreat.com

All the site contents are Copyright © www.erpgreat.com and the content authors. All rights reserved.
All product names are trademarks of their respective companies.  The site www.erpgreat.com is in no way affiliated with SAP AG. 
Every effort is made to ensure the content integrity.  Information used on this site is at your own risk. 
 The content on this site may not be reproduced or redistributed without the express written permission of 
www.erpgreat.com or the content authors.