Change Base Unit of Measure
in MM
One raw material we assigned base unit of measure as
OZ, later add alternate unit of measure as ML.
Now I wanted to change the base unit to ML and alternaet
to OZ. For that I deleted component from the BOM. Related PO's,
Prd ord and demand are closed. Deleted the alternate unit from purchasing
and plant/stock (Area were we assign the alternate unit), then try to change
it giving message as Unit of measure ML used as alternate unit. (In
additinal data screen still the alternate unit and conversion available)
By: Vidhya
You can do the following procedure (after deleting the
material in all concerened documents):
1. Delete the uom from Unit of issue field (General Plant
Data / Storage 1) in MM if you have mentioned it there.
2. Go to additional data , use delete line tab and delete
the conversion factor by keeping the cursor on that line.
3. Come to main data, now change the base unit of measure
to the required one.
4. Then give the alternative unit of measure, system will
ask for conversion factor.
5. Then save
You can only change the base units of measure under the
following circumstances:-
- No stocks are available for the material.
- There are no existing purchase requisitions, purchase
orders, or scheduling agreements for the material.
- At present, no purchase orders or purchase order items
are being created or changed.
If requests for quotations, purchasing info records,
or contracts are available for a material, the system gives a warning while
changing base unit of measure. Still if you want to change unit of measure
specify in a dialog box the factor for converting the base unit of measure
into the new base unit of measure. The purchasing info records are then,
if necessary, updated.
1) If there are stocks in the
previous period, you can clear them as follows:
a) Post the stock in the previous
period to the current period e.g. 010799 (for example, using
movement type 561) so that the stock for the previous period is the same
as the stock for the current period.
b) Clear the stock with the
posting date in the previous period e.g. 300699 (for example,
using movement type 562).
2) If there are Open purchase requisitions, purchase orders,
or scheduling agreements for the material.
- Run MM02 (Change Material Master immediately).
- Overwrite the old base unit of measure with the new
one in basic data screen.
- Save the change.
- System checks
If a change criterion (MM02) is meeting all necessary
prerequisites (as mentioned in point 1).System allows changing base unit
of measure. Otherwise it displays warning or error. You can display
the reason for this, by choosing Display Errors (ctrl+F1)
Related
Get help for your SAP MM problems
Do you have a
SAP MM Question?
SAP MM Books
SAP Material
Management Certification, Interview and Configuration Reference Books
SAP Material Management Tips
SAP MM Configuration
Tips and Materials Management Discussion Forum
Best regards,
SAP Basis, ABAP Programming and Other IMG Stuff
http://www.erpgreat.com
All the site contents are Copyright © www.erpgreat.com
and the content authors. All rights reserved.
All product names are trademarks of their respective
companies. The site www.erpgreat.com is in no way affiliated with
SAP AG.
Every effort is made to ensure the content integrity.
Information used on this site is at your own risk.
The content on this site may not be reproduced
or redistributed without the express written permission of
www.erpgreat.com or the content authors.
|