How To Create PO From PR With Ref to Contract

Creation of Purchase Requisition With Reference to Contract Documents :

You cannot create PR directly from Contract as a reference document.

You can use it as a Source of Supply.

During manual creation of PR (ME51N), you have to enter all the details like material, qty, plant, purchase grp, etc... manually and under Source of Supply Tab at item details level, specify the Contract document no.

And you can also create PRs using contract through MRP, for this maintain Source List (ME01), here specify Contract document no for the source line and also maintain MRP indicator as "1" or "2" and after MRP Run (MD02), check PRs, they will have contract no in Source of Supply Tab.

Steps to Manually Assign Contract from Purchase Requisition :

1. Logistics----Materials Management----Purchasing ---Purchase Requisition --Follow-on functions --- Assign and Process

2. ME57 

3. Select the Assigned Purchase Requisitions checkbox if you also want to see requisitions already assigned, and choose Execute.

4. On the Assign and Process Purchase Requisitions screen, select the requisition lines for your material.

5. Choose Assign Manually if the info record already exists.

6. On the pop-up Assign Source of Supply Manually dialog box, make the following entries:
Agreement 46XXXXX Agmt item 10 

7. Choose Assign Source of Supply.
For assign the source of supply, you can also choose Assign Automatically (only if not already assigned by MRP due to existing source list). If more than one source exists, select the contract in the Source Overview for Purchase Requisition 100XXXXX window and confirm with Enter.  When assigning a source, make sure to select the contract.

8. Choose Save. 

9. Select the line item, and then choose Assignments Overview (SHIFT+F5). 

10. On the Assign and Process Requisitions: Overview of Assignments screen, select the line below Vendor (you can only select one at a time), then choose Process Assignment. 

11. On the Process Assignment: Create PO window, check and make sure the Order Type (NB), Purchasing Group and Purch. Organization fields then choose Continue (Enter) to confirm.

12. On the Create Purchase Order screen, select the requisition in the Document Overview section and choose Adopt in the left part of the Document Overview screen.

13. Choose Save. 

SAP MM Tips

Get help for your SAP MM problems
SAP MM Forums - Do you have a SAP MM Question?

SAP MM Books
SAP Material Management Certification, Interview and Configuration Reference Books

SAP Material Management Tips
SAP MM Configuration Tips and Materials Management Discussion Forum

Main Index
SAP Basis, ABAP Programming and Other IMG Stuff

All the site contents are Copyright © www.erpgreat.com and the content authors. All rights reserved.
All product names are trademarks of their respective companies.  The site www.erpgreat.com is in no way affiliated with SAP AG.
Every effort is made to ensure the content integrity.  Information used on this site is at your own risk.
 The content on this site may not be reproduced or redistributed without the express written permission of
www.erpgreat.com or the content authors.