What are the procurement cycle (stepwise) of imported material up to GR(101)? What are the steps that are to be followed to reverse the GR for imported material?  What are the transaction used?

1) The procedure for imported material receipt is as follows.....

        a) P.O. Generation for the material.     ME21n
        b) Capture planned delivery cost         MIRO
        c) Capture excise invoice                     J1IEX
        d) Goods Receipt                                MIGO

Since we are capturing the planned delivery cost for the GR (through MIRO) . So before returning the material we have to reverse the planned delivery cost thru "Subsequent Credit " using MIRO. Then only return thru MIGO will be possible.

So, the steps for cancelling the documents for imported material is:

2)    a) Sub sequent credit  using                   MIRO
        b) Return GR (delivery) using               MIGO
        c) Cancell the excise invoice using        J1IEX

These are the steps to return the imported material & cancel the Excise Invoice capture.      *-- B.Anand daivaraja 

Get help for your SAP MM problems
Do you have a SAP MM Question?

SAP MM Books
SAP Material Management Certification, Interview Questions and Configuration Reference Books

SAP Material Management Tips
SAP MM Configuration Tips and Materials Management Discussion Forum

Best regards,
SAP Basis, ABAP Programming and Other IMG Stuff
http://www.erpgreat.com

All the site contents are Copyright © www.erpgreat.com and the content authors. All rights reserved.
All product names are trademarks of their respective companies.  The site www.erpgreat.com is in no way affiliated with SAP AG.
Every effort is made to ensure the content integrity.  Information used on this site is at your own risk.
 The content on this site may not be reproduced or redistributed without the express written permission of
www.erpgreat.com or the content authors.