In ME23N what is the difference between PO Quantity
and Scheduled Quantity?
Ans: PO Quantity which is known as committed quantity by vendor to supply as and when on or before specific delivery date. Scheduled Quantity is the quantity to be delivered by
the vendor in respect of schedule line as planned. The total PO quantity
can be dragged and partially divided into different segment of delivery
date for different quantum of material .This quantity is referred to by
GR and IV for checking purposes also.
When do we need a new document type in purchase order? Ans: 1) Suppose you want a separate report for import PO and domestic Po in t-code like ME2N, ME2L. In that case we have to define new Po document type so we can get report by document type and same will applicable to Asset purchasing also. 2) You want different pricing procedure assignment in MM, then in that case PO document will help like import and domestic pricing procedure. 3) Suppose in service PO user may forget to use item categories
D or he may used different item categorizes other than D, so in that case
we can define new document type and allow only item categories D so he
cannot use the wrong item categories in PO.
How many Po type are there? Ans: In purchasing document types are divided in two types: a) Internal purchasing document Example: purchase requisition b) External purchasing document Example: quotation, purchase order, contract, schedule
agreement.
At which level is the purchase order history kept?
Ans: PO history is updated in table: EKBE and if you go to see, there is a field client and purchasing document/plant. PO history updation depends upon transaction and event type where there are different type of transaction key: 1 Goods Receipt 2 Invoice Receipt 3 Subseq. Debit/Credit 4 Down Payment 5 Payment 6 Goods Issue for Stock Transfer 7 Consumption (Subcontracting) 8 Delivery (Stock Transfer) 9 Service Entry Sheet A Down Payment Request C Down Payment Clearing Q Comparison for Internally Posted Material (Only IS-OIL) R Return Delivery via Delivery Note P Invoice Parking V Down Payment Request Clearing
You can see that PO history is updated at PO line item level and also see it at the header level then in status tab, you can see the the following gets updated - Ordered - Delivered - Still to delivered - Invoiced - Down paymts
Where is the purchase order text stored? Ans: It is stored in the tables STXH, STXL. Text gets
stored as object ID and text ID.
How to edit created P.O.? If user want to change some data like price, data etc. in a created purchase order but system is not allowing it. As a support SAP MM functional consultant what you would do? Ans: This is an open question without direct answers and you should suggest the possibilities: If you have made goods receipt against PO, then you cannot make any change to the price and other condition details in PO if not you will be able to do it. Also, check whether user have authorisation for ME22N. The Price came from Inforecord (if you have maintained the inforecord for material and vendor combination), then in this case you cannot directly change the Price in PO. If you want to change then check PO condition type is it PBXX, then you can change. There is a procedure called as the field selection. When a purchase order is created, then it requires a release. In the release procedure you can maintain the fields which cannot be changed as per the field selection. For example, if I am an approver and I approved a purchase order for 10 pieces and released it, in this case if the changes are allowed for the quantity then the total release procedure becomes useless. |
|
See also
SAP MM Forums - Do you have a SAP MM Question? SAP MM Books
SAP Material Management Tips
Main Index
All the site contents are Copyright © www.erpgreat.com
and the content authors. All rights reserved.
|