1) Your project uses production
costing and production planning functionality.
Which valuation area must be used? a. Company code
Which is the correct answer? --- Explanation: You define the valuation level by specifying the level at which material stocks are valuated. You can valuate material stocks at the following levels. Plant level Valuation must at this level in the following cases:
The decision you make is valid for the whole client. You are recommended setting material valuation at plant level. --- Answer: 1) c
|
|
See also
Get help for your SAP MM problems
SAP MM Books
SAP Material Management Tips