Work Center Capacity In Graphical Form

Having a scenario with reference to planned maintenance which is as follows:

The maintenance plan will be created with start dates, after attaching task list with different frequency for different activities.
Now we would like to if there is any way of a user knowing before scheduling if the planned time is in excess of a work center capacity.

By: Graham Johnston

Use IP19

This will simulate the maintenance plans and allow you to see work center capacity in a graphical form. 

Set up your search criteria and make sure you select Items & tasklists.

Set up your search criteria

Once in there select Weekly Capcity Load  and you should see a capacity by Work Center. You can also do monthly.

Weekly Capcity Load

See Also
Maintenance Planning  Questions and Answers

Have a SAP PM Problems?
SAP PM Forum - Do you have a SAP PM Question?

SAP Plant Maintenance Books
SAP PM Books - Certification, Interview Questions and Configuration

SAP PM
SAP PM Tips and Plant Maintenance Discussion Forum

Main Index
SAP ERP Modules, Basis, ABAP and Other IMG Stuff

All the site contents are Copyright © www.erpgreat.com and the content authors. All rights reserved.
All product names are trademarks of their respective companies.  The site www.erpgreat.com is in no way affiliated with SAP AG.
Every effort is made to ensure the content integrity.  Information used on this site is at your own risk.
 The content on this site may not be reproduced or redistributed without the express written permission of
www.erpgreat.com or the content authors.