Having a scenario with reference to planned maintenance
which is as follows:
The maintenance plan will be created with start dates,
after attaching task list with different frequency for different activities.
By: Graham Johnston Use IP19. This will simulate the maintenance plans and allow you to see work center capacity in a graphical form. Set up your search criteria and make sure you select Items & tasklists.
Once in there select Weekly Capcity Load and you should see a capacity by Work Center. You can also do monthly. |