I have created my storage location as MRP area in the
customizing. Now when I am trying to enter in the MRP 1 view in material
master, it is showing the following error.
To create storage location MRP area, do the following steps: 1. Create MRP area by SPRO -> MRP -> Master data -> MRP
area -> Define MRP area.
2. Define scope of planning by tcode OM0E.
3. In MM02 assign MRP area in MRP1 view. 4. In SPRO -> Define parallel processing in MRP. 5. While MRP run, select parallel processing in the initial screen. If you want to run MRP only for one MRP area then only
enter the MRP Area there or If you want to run MRP for Plant with MRP area,
several MRP area you can
Run MRP with MD01 then.
What exactly is the use of transaction code OM0E and What is the use of defining scope of planning. In scope of planning (OM0E) :- you can define: 1. Several plants
If you want to run MRP for a plant, you can enter a plant as normal. But if you want to run multiple plant or other option, you have to create scope of planning. So that MRP plan for Multiple plants. Do you know of a program/transaction (like MASS) that will enable me to update Material master MRP Area data (table MDMA)? Try report RMMDDIBE - Fill in the MRP Area Data
Get help for your SAP PP Problems
SAP Production Planning Books