Production Resources Tools Self Review Questions and Answers

Select the correct answers to these SAP PP relevant questions on Production Resources Tools.

1) The R/3 System differentiates between the following types of production resources/tools, according to their properties and business function:

A. Materials that are accounted for in materials management, for instance in inventory management, requirements planning and procurement.
B. Equipment, for instance measuring instruments or valuable tool, which are serviced
C. Documents, for instance drawings or programs, which use the document management system.
D. Miscellaneous production resources/tools (with a PRT master record), that require less maintenance in the system.
 

2) For information about how to classify the other PRT categories, as follow:

A. for materials - LO - Managing material Master Data
B. for equipment - PM - Structuring Technical Systems
C. for documents - CA - Document Management Guide
 

3) You use production resources/tools (PRT) that have an equipment master record you can,

A. plan and monitor the wear of the PRT
B. create a maintenance plan that accounts for the PRT
 

4) You create the following information for the maintenance planning of PRTs:

A. a PRT wear counter that gives information about the level of wear for a PRT.
B. the wear to be expected for each operation
C. an activity related maintenance plan
 

5) You can only delete a production resource/tool (PRT)

A. if it is no longer assigned to an operation
B. if it is no longer linked with a document
C. None of above
 

6) For information about how to set deletion flags for the other PRT categories, as follow:

A. for materials - LO - Managing Material Master Data
B. for equipment - PM - Structuring Technical Systems
C. for documents - CA - Document Management
 

7) The PRTs must have a master record in the system. According to the PRT category the following conditions have to be met additionally:

A. Materials, equipment and documents must be released, using their status, as production resources/tools.
B. Production resources/tools with a PRT master record must be released in their status for use in resource planning.
C. PRTs with material masters, PRT masters or equipment masters must be intended for use in routing in their task list usage.
 

8) The R/3 System distinguishes between the following types of production resource/tool on the basis of their attributes and business function:

A. Materials considered in materials management, for as follow: in inventory management, material requirements planning, and procurement.
B. Equipment such as measuring devices or high-quality tools requiring preventive maintenance.
C. Documents such as drawings or programs for which document management functions are used.
D. Other PRTs (with a PRT master record) requiring less maintenance.
 

9) In the following objects, you can assign PRTs to operations and phases:

A. Task lists (including standard networks and recipes)
B. Production orders and maintenance orders
C. Networks

---

Correct Answers

1) A, B, C, D

2) A, B, C

3) A, B

4) A, B, C

5) A, B

6) A, B, C

7) A, B, C

8) A, B, C, D

9) A, B, C

SAP PP Tips

See also

Get help for your SAP PP Problems
SAP PP Forum - Do you have a SAP PP Question?

SAP Production Planning Books
SAP PP Certification, Interview Questions and Configuration Books

SAP PP Tips
SAP PP Tips and Production Planning/Control Discussion Forum

Main Index
SAP ERP Modules, Basis, ABAP and Other IMG Stuff

All the site contents are Copyright © www.erpgreat.com and the content authors. All rights reserved.
All product names are trademarks of their respective companies.  The site www.erpgreat.com is in no way affiliated with SAP AG.
Every effort is made to ensure the content integrity.  Information used on this site is at your own risk.
 The content on this site may not be reproduced or redistributed without the express written permission of
www.erpgreat.com or the content authors.