Please refer above subject and would like to do following. External Processing Time I have set in using OPPQ. My client want this time set differently for different Vendor. Is there any userexit or customization settings? 

For MRP to take lead time by supplier, you need to have 3 settings: 

1) The config in OPPQ - External procurement at plant level (or OPPR at MRP grp - Scheduling/doc. type) should have the check box marked to read SchedAgreem/Inforecord leadtime (T399D-GTERM) 

2) You should have a contract/schedule agreement, or a purchase info record maintained for that plant-material-vendor combination 

3) You should maintain source list (ME01) for the contract/schedule agreement, or info record. This changes the default behavior of MRP to use leadtime by supplier, rather than material master leadtime. When both contract and info record exist, the contract will take precedence. 

Please watchout for the case if you're already using contracts/info records in procurement, but not using them for planning. In this case your leadtime data in these documents may be incorrect, or may be left blank - this will be interpreted as zero if you make this change implementation, as mentioned in the steps above. 

Related Links:
Understanding the MRP Rescheduling date
Rescheduling date does not take into account the GR Processing Time

Get help for your SAP PP Problems
Do you have a SAP PP Question?

SAP Books
SAP Certification, Functional, Basis Administration and ABAP Programming Reference Books

SAP PP Tips
SAP PP Tips and Production Planning/Control Discussion Forum

Main Index
SAP Basis, ABAP Programming and Other IMG Stuff
http://www.erpgreat.com

All the site contents are Copyright © www.erpgreat.com and the content authors. All rights reserved.
All product names are trademarks of their respective companies.  The site www.erpgreat.com is in no way affiliated with SAP AG. 
Every effort is made to ensure the content integrity.  Information used on this site is at your own risk.
 The content on this site may not be reproduced or redistributed without the express written permission of 
www.erpgreat.com or the content authors.