Rough Cut Capacity Load In Standard SOP

Problem:

Have created some sales & production plan synchronous to sales but when I try to see the capacity load thru:
View -> Capacity Situation -> Rough Cut planning -> Show
It is showing me that No Resource load exists.

Resolution:

Please maintain the settings as mentioned below.  Then you can see the load.

Before you can carry out resource leveling in SOP, you must:

1.) Create a PP task list (a routing, a rate routing, or a rough-cut planning profile) for the material, product group, or characteristic values combination whose resources you want to plan.

2.) Configure resources planning in Customizing for Sales & Operations Planning.

3.) If you use routings or rate routings to do resource leveling, define the key figure to which the resources are tied. Do this in Customizing for Sales & Operations Planning under Set parameters for info structures and key figures.

4.) Define the planning plant of any information structure whose plant is not uniquely identifiable (that is, either your information structure does not contain the characteristic "plant" or your rough-cut planning profile covers more than one plant). Do this in Customizing for Sales & Operations Planning under Set parameters for info structures and key figures.

5.) Set the default SOP plant for Sales & Operations Planning. Do this in Customizing for Sales & Operations Planning under Set planning plant for SOP.

Note:

Follow these detail steps:

1. Create a product group (mc84)

2. Create a production plan (mc81). 

Enter a qty in sales plan row.

Goto Edit->create prodn plan synchronous to sales plan.

3. Create rough cut planning profile (mc35).

Here choose the resources as the bottleneck work center & enter the time to produce 1 pc.

4. In mc82, go to views -> capacity situation -> show

You can see the load % in the bottom. Adjust your requirement so as to match the load for 100%.

5. Then use mc78, enter the inactive version Eg:01/02 & enter the inactive version as a00 & then click transfer/copy.

6. In mc82 screen you can see that the plan is in active mode.

7. Now in the same screen, goto Extras->transfer to demand management.

Here enter the requirement type & then click transfer.

7. In md61/md62 you can see the requirement.

SAP PP Tips

Get help for your SAP PP Problems
SAP PP Forum - Do you have a SAP PP Question?

SAP Production Planning Books
SAP PP Certification, Interview Questions and Configuration Books

SAP PP Tips
SAP PP Tips and Production Planning/Control Discussion Forum

Best regards,
SAP Basis, ABAP Programming and Other IMG Stuff
http://www.erpgreat.com

All the site contents are Copyright © www.erpgreat.com and the content authors. All rights reserved.
All product names are trademarks of their respective companies.  The site www.erpgreat.com is in no way affiliated with SAP AG.
Every effort is made to ensure the content integrity.  Information used on this site is at your own risk.
 The content on this site may not be reproduced or redistributed without the express written permission of
www.erpgreat.com or the content authors.