Step by Step Process Of MRP Flow

From Demand management, how the MRP flow starts.  Since MRP is contributing with many inputs in material master, how are the importance data taken.  Explain clearly the Step by Step flow.

Answer:

The Process Flow:

1. The system calculates net requirements for all the requirement quantities that are to be planned. The system thereby compares available warehouse stock or the scheduled receipts from Purchasing and Production with planned independent requirements, material reservations and incoming sales orders. In the case of a material shortage, that is, if the available stock (including firmed receipts) is smaller than the quantity required, the system creates procurement proposals.

2. The system calculates the quantity recorded in the procurement proposal according to the lot-sizing procedure that you specified in the material master. Various lot-sizing procedures are supported by the system. You can define a lot-sizing procedure for each individual material.

3. The procurement proposal is also scheduled which means that, for materials procured externally, the delivery and release dates are determined, and for materials produced inhouse, the production dates are calculated.

4. For materials produced in-house, the dependent requirements of the components are determined during the BOM explosion. For each component, the dependent requirements date is displaced by the in-house production time of the higher-level material.

5. Additional requirements (unplanned goods issues, excess consumption of components in production, and so on) can be covered by using the materials forecast within MRP. The historical values of unplanned requirements form the basis of the forecast. These requirements are then taken into account along with the exact requirement quantities.
 

The whole production process takes place in the following steps.

1) Forecasting of the future demand.

2) Demand Planning (Flexible planning / Standard SOP).

3) Transfer Demand Planning data to Demand Management.

4) Demand Management.

5) MRP - Material requirement planning will happen in the following steps:
a) Net requirements are calculated
b) based on the various configuration parameters like the requirement type, planning strategy & MRP type...etc, planned orders are generated with schedule dates & quantities.

6) Capacity Planning.

7) Conversion of Planned Orders to Production Orders & execution.

In short this is the whole process of planning. 

Get help for your SAP PP Problems
SAP PP Forum - Do you have a SAP PP Question?

SAP Production Planning Books
SAP PP Certification, Interview Questions and Configuration Books

SAP PP Tips
SAP PP Tips and Production Planning/Control Discussion Forum

Best regards,
SAP Basis, ABAP Programming and Other IMG Stuff
http://www.erpgreat.com

All the site contents are Copyright © www.erpgreat.com and the content authors. All rights reserved.
All product names are trademarks of their respective companies.  The site www.erpgreat.com is in no way affiliated with SAP AG.
Every effort is made to ensure the content integrity.  Information used on this site is at your own risk.
 The content on this site may not be reproduced or redistributed without the express written permission of
www.erpgreat.com or the content authors.

SAP PP Tips