|
What is finite and infinite scheduling? How
it is carried out? What is to be done for each one? What are their
significance?
Differences between planning and scheduling, finite and infinite Finite Scheduling Scheduling type within capacity planning that takes account of the capacity loads which already exist. Finite scheduling calculates the start and finish dates for operations in the order. It is a detailed scheduling strategy with which you schedule orders and operations, taking into account the existing resource load. A resource overload cannot occur. Infinite Scheduling A detailed scheduling strategy with which you schedule orders and operations, without taking into account the existing resource load. It is therefore possible for resource overloads to occur. R/3 does planning without consideration for capacity situations. So if MRP says you need 500 parts on 3/1/04, it schedules them all to be built at the same time, even though you can only do 100 at a time. Assume you have a fixed lot size of 100, you'll get 5 planned orders for 100 to start on the same day. This is "Infinite Planning". APO would recognize that constraint, and instead schedule out the 5 orders over time. The important part of that is that it also will schedule out the deliveries of the components for 5 different days. This is "Finite Planning". Now, assume old fashion MRP. It schedules all 5 orders
for the same day, and the buyers go out an get all of the components for
the same day. Then the planner realizes he can't do all 5, and manually
changes the schedule, and manually spreads out the 5 orders. The buyers
will recieve rescheduling notifications, but not until the scheduler does
the manual rescheduling.
But, SAP has "Capacity Leveling". What that means is you
run another program after MRP (CM27 and CM28), which can be run in batch
mode overnight. (There is a ton of configuration and thinking that will
be required to do this!). The capacity leveling program will recognize
the constrant at the work center level, and fill up the first day, then
re-schedule the next
Finite Planning does Finite Scheduling at the same time.
If there is no capacity available on the desired date, the system looks
for when capacity IS available. Then it stops to see if Materials will
also be available (usually based on the lead-time for those components).
If there is a material problem, then the system figures out when the materials
WILL be available, and then
SAP PP Tips by : Nagesh
See also
Get help for your SAP PP Problems
SAP Books
SAP PP Tips
Main Index
All the site contents are Copyright © www.erpgreat.com
and the content authors. All rights reserved.
|