When we confirm activities and see it in cns41 report we can see that the POC is aggregated at the Network,WBS and porject level.  How does the system calculate this.. i.e on what factors and criteria?

Result analysis determines the costs & revenues belong to the period, along with the Work in progress (WIP) or Reserves.

Result analysis calculation is based on the planned / actual Cost & Revenue. 

POC (Percentage of Completion) determines by the valuation method you opt …

The formula for POC :

  POC = R (a) / R (P) Revenue Proportionate

  POC = C (a) / C (p) Cost Proportionate 

Result Analysis Determines:

- Calculated Costs C(c) = POC X C (p) Same for Revenue 
- WIP (If C(a) >C (c) ) WIP = C(z)= C(a) - C(p)
- Reserves for unrealized costs (if C(a) < C(c) )
   C( r ) = C (c ) – C(a) 
- Revenue Surplus (if R (a) > R(c) ) 
   R (r) = R(a) –R(c) 

E.g.

Revenue Proportionate RA: 

In some project you have R(p) =3000$
  C (p) = 2000$
  R (a) = 1200$
  C (a) = 1000$

Then POC = 1200 /3000 = 40 %

C(c) = POC X C(p) = 40 % X 2000 = 800$

WIP = C(z) = C(a) –C(c) = 1000-800 =200$

Tips by : Nikhil

Get help for your SAP PS problems
Do you have a SAP PS Question?

SAP Reference Books
SAP Certification, Interview Questions, Functional, Basis Administration and ABAP Programming Reference Books

SAP Project System Tips
SAP PS Tips and Project System Discussion Forum

Best regards,
SAP Basis, ABAP Programming and Other IMG Stuff
http://www.erpgreat.com

All the site contents are Copyright © www.erpgreat.com and the content authors. All rights reserved.
All product names are trademarks of their respective companies.  The site www.erpgreat.com is in no way affiliated with SAP AG.
Every effort is made to ensure the content integrity.  Information used on this site is at your own risk.
 The content on this site may not be reproduced or redistributed without the express written permission of
www.erpgreat.com or the content authors.