1) What are functional areas that
SAP EPPM Project System can interact with during the planning and execution
of a project in SAP S/4HANA?
a. SAP Enterprise Resource Planning
Which are the correct answers? --- 2) What are usually the first steps when creating a new project? a. Planning the capacity and allocating
the budget
Which are the correct answers? --- 3) You don't want to create a project structure from scratch. What can you use to assist you when creating a project? a. A template
Which are the correct answers? --- 4) Which functional areas of SAP S/4HANA are directly connected to Project Management for the types of projects discussed here? a. Manufacturing
Which are the correct answers? --- Answer 1) c, d, e 2) c 3) a 4) c, d, e
|
|