CNMASS is the standard transaction
to carry out mass change of WBS elements, network, activities, activity
elements, relationships, milestones.
Can we change the values dynamicallty in cnmass? Yes, you can change values dynamically. Run CNMASS --> Shift + F4 (dynamic selection window) will open, you can check the values from here. The values available only in this dynamic selection only can be changed For ex. System status you cannot chagne in CNMASS.
Function module for ABAP You can use : BAPI_BUS2054_CHANGE_MULTI : Change WBS Element BAPI_BUS2002_ACT_CREATE_MULTI : Create one or more activities
Authorization Role The standard role SAP_PS_MASS_CHANGE SAP_PS_MASS_CHANGE Mass Change Standard Cross-application Authorization Objects Standard Transaction Code Check at Transaction Start Transaction Code CNMASS, CNMASSPROT Standard Project System Standard PS: Transaction-Specific Authorizations in Project System Department for authorization - General data (integrated edit and evaluation) Transaction type Display, Change
Question for you: In “Mass Change” Function you can change followings: a) Project Definition b) WBS Element c) Network d) Activities e) Relationship |
|
See Also
Get help for your SAP PS problems
SAP Project System Books
SAP Project System Tips
Main Index
All the site contents are Copyright © www.erpgreat.com
and the content authors. All rights reserved.
|