Sequence Of Operations To Get EVA

In my project system I want project progress analysis on the basis of only time proportionality.  Cost will not be consider for progress andtheir are different units used like m, m3, km & hr for work in internal & external activities, so is it possible to do such setting on the basis of confirmation in customisation? 

Yes it is possible do through activity confirmation.  It all depends on EV basis, their you need to set time proportionality.

You need to perform sequence of operations to get EVA. for time prop. you need to maintain scheduling, activity confirmation etc.

Define default meas method as Time prop for objects in customising.

You need to do customization settings for EVA for progress version, statistical key figures, value catagories, progress cost element etc. 

You can go the following customizing steps... this will help you to configure as per your needs. This is not as per your need, as only you can understand what all the customizations you need to do........

1. Create Progress Version 101 with exclusive use 'Progress Analysis'. I have selected Plan & Actual check boxes. 
2. Settings for Progress Version- 
a) Plan version - '0' 
b) EV basis - Cost plan (active project, annual values) 
c) POC weighting - Cost plan (active project, annual values)
d) Planning type - Basic dates 
e) Early / Late - earliest possible 
f) Both reference boxes selected 

3. SKFs- I created three SKFs 10 (Non-Aggregated POC), 20 (Aggregated POC) and 30 (POC for RA) with unit of measure '%' and selected the Key value category 'Total values'. 

4. I need to assign these SKFs to different value categories. I created three value category 10, 20 & 30 with selection 'SKF with total values' and unit of measure '%'. Then I assigned SKF 10 to VC 10, SKF 20 to VC 20, SKF 30 to VC 30

5. I assigned measurement method as default value: 
a) WBS (Plan) - Cost Proportional 
b) WBS (Actual) - Cost Proportional 
c) Internal Activity (Plan) - Cost Proportional 
d) Internal Activity (Actual) - Degree of Processing 
c) Exernal activity(Plan) - Cost Proportional 
d) Exernal Activity (Actual) - Degree of Processing 

6. I made progress cost element '6511100' (Secondary cost element) with Cost element category as 61. 

7. I maintain a value catagory 6511100 with Cost radio button selected.
And assigned the progress cost element to the value catagory. i.e Cost element 6511100 to value catagory 6511100.

8. I maintain the assignment of cost element group. ie. I assigned progress cost elemnt to cost element group with default radio button selected. In the cost element group, I have selected certain cost elements which we regularly used (cost elements for project materials, project manhours, project contracts, spares etc)

Run CJEN first then CNE1 and CNE5.                                       *-- Madhu

Get help for your SAP PS problems
SAP PS Forum - Do you have a SAP PS Question?

SAP Project System Books
SAP PS Books -  Certification, Interview Questions and Configuration

SAP Project System Tips
SAP PS Tips and Project System Discussion Forum

Best regards,
SAP Basis, ABAP Programming and Other IMG Stuff
http://www.erpgreat.com

All the site contents are Copyright © www.erpgreat.com and the content authors. All rights reserved.
All product names are trademarks of their respective companies.  The site www.erpgreat.com is in no way affiliated with SAP AG.
Every effort is made to ensure the content integrity.  Information used on this site is at your own risk.
 The content on this site may not be reproduced or redistributed without the express written permission of
www.erpgreat.com or the content authors.