Short Questions Answers on SAP PS

Project Calculations

When we confirm activities and see it in cns41 report we can see that the POC is aggregated at the Network,WBS and project level.

How does the system calculate this.. i.e on what factors and criteria?

PS, like, other Projects Programs used the Pondered advance has a project and structural (WBS) phisical advance.
IF you have a Project with only 1 activitie. The 100% phisical advance of the activitie is passed to the Project.
If you have a Prj. with 2 activities and both had 100% phisical advance.  The project has 200%? NO!, PS calculated this

Percent complete Activity A = 100 = A-POC
Percent complete Activity B =100    B-POC
Weigth or contribution of A = 30%     A-Wgt
Weigth or Contribution of B =70%      B-Wgt
(The sum of the weigth need to be 100%)

The Project Advance will be A-POC*A-wgt + B-POC*B-Wgt 
This implies =  100*30% + 100*70% = 30 + 70 =100

The weigth is a function of Men-Hours, Cost or Special-Weigth.  *-- NelsonHM

User Status Report

In the business scenario used here a status profile containing different User statuses with authorisation controls has been set up in the Project Definition for controlling the process of Project creation & approval. The process flow is as follows - The project is created by the design team, after which it is sent to pre-audit team for approval, the pre-audit team approves it, on approval the project is released and the rest of the process flows on.  Each of the above phases is marked by an user status and on completion of a phase the user sets the next user status for the object. 

Requirement : An ABAP report is required to be developed which shows the date and time at which each of the user staus was set and released. 

Go to transaction SE38, and enter RBSVCDOC in the field "Program". Select the Execute button. Insert your WBS's object number, and select the tick box "SHOW_ALL" Execute the program.

If the results is what you are looking for, then follow these steps to have your required report on User Status Change Log:

1. Ask your ABAP program to copy function RBSVCDOC to a Z-Program, and 2. assign a Z-transaction code this copied Z-program. 3. You can also ask the programmer if he is able to design a user defined input screen to this program.

*-- Pieter LP van Sittert

Creating an Internal Activity at the Network Level

Trying to create an internal activity at the network level and whenever I go to the menu to add an internal activity, the level moves up to the project level instead of remaining at the nework level.  This of course prevents me from creating the internal activity.  Why this is happening?

Work out the following path :
1) Go to "Structure Tree" (Top-left pane of Project Builder), click on Network Header.
2) In "Work Area" (Right pane) click on "Activities Overview" icon. Go to "Int. Processing Tab" and define activity with relevant field details and Confirm.

This will create Int activity in the selected Network only.  *-- Nabada More

Time calculation in work Center 

My requirement is to calculate the time taken for a component which contains 4 Operations.  Using Work Centers in PS Module.

  Details of the Operations:
  1. Chain cutting
  2. Soldering
  3. Lock fitting
  4. Assembly

Time taken for soldering operation = 15 sec/soldering operation
One component contains = 20 soldering operation
Total time taken to finish one component = 300 sec
In one day  we can make = 8 hr(28800sec)/300sec=96 nos.

How we can calculate this in the system Using Work Center.

  You need to do folowing....
  1) Define 4 activity type with these names and give the unit of operation as second - and assign it to a cost center in kp26 
      with cost
  2) Define a work center in CNR1...using usage project management 0006
  3) Assign formulae SAP004 in the other formulae in scheduling tab and SAP008 in capacity Tab.
  4) Assign working hours for your WC in capacity tab header data as 8 hours and put number of available capacity
      (no.of people in Work center)
  5) Assign all the activity types in the Work center costing tab
  6) Give duration for all these activity in your project 
  7) Schedule the project and do costing....   *-- Ritesh Bhushan

Fast Links:
Get help for your SAP PS problems
Do you have a SAP PS Question?

SAP Books and Training CBT
SAP Project System, Functional, Basis and ABAP Programming Reference Books

SAP Project System Tips
SAP PS Tips and Project System Discussion Forum

Best regards,
SAP Basis, ABAP Programming and Other IMG Stuff
http://www.erpgreat.com

All the site contents are Copyright © www.erpgreat.com and the content authors. All rights reserved.
All product names are trademarks of their respective companies.  The site www.erpgreat.com is in no way affiliated with SAP AG.
Every effort is made to ensure the content integrity.  Information used on this site is at your own risk.
 The content on this site may not be reproduced or redistributed without the express written permission of
www.erpgreat.com or the content authors.