Steps to take in order to force-close PO 

There are two ways to force close a PO: 

1. You can set Delivery Completed Indicator in Purchase Order or at time of doing goods receipt. That simply means you cannot do further GR for that item. You can still process Open Invoices . 

2. You can block material at purchase order level which means, you will not be able to do any GR , Invoice against that specific item in PO.

The recommended is the first option though.

Second option is used in case of : - 

1. to cancel an item
2. An item is closed and can be archived

Fast links:
SAP MM Questions

Get help for your SAP MM problems
SAP MM Forums - Do you have a SAP MM Question?

SAP Books
SAP Certification, Functional, Basis Administration and ABAP Programming Reference Books

SAP Material Management Tips
SAP MM Configuration Tips and Materials Management

Best regards,
SAP Basis, ABAP Programming and Other IMG Stuff
http://www.erpgreat.com

All the site contents are Copyright © www.erpgreat.com and the content authors. All rights reserved.
All product names are trademarks of their respective companies.  The site www.erpgreat.com is in no way affiliated with SAP AG. 
Every effort is made to ensure the content integrity.  Information used on this site is at your own risk. 
 The content on this site may not be reproduced or redistributed without the express written permission of 
www.erpgreat.com or the content authors.