External Operation Processing

1. For a production material (1001), one raw material (2001) is assigned. 

2. Production process of 1001 is having four operations 10, 20, 30 and 40. 

3. In this 10, 30, and 40 are internal operations and 20 is external operation (sub-contracting). 

4. To address this, we created a dummy material (non-valuated) and named as 1001-20 (Finished product number + Operation to be performed). 

5. This 1001-20 should form part of the component in BOM of 1001. That is BOM of 1001 will have components as raw material 2001 and this dummy material 1001-20. In routing, assign this dummy material 1001-20 to operation 20. 

6. During BOM creation, you should remove costing relevancy for the item 1001-20. 

7. In routing, operation 20 is created with a work center (which is external operation work center) with external operation control key. 

8. In operation details, for external processing, assign the info record of external processing. 

9. Info record of external processing has to be created for vendor with relevance to the operation to be performed externally with vendor. (We are using material group field in the external processing in routing operation). 

10. When create production order with above set up, system will create Purchase Req for external operation. This has to be converted to purchase order. 

11. Now, this dummy material should be kept as 5000 or 6000 in stock using 561. When Purchase order is raised, required quantity has to be moved to vendor using 541. When we do goods receipt the stock with vendor shall come down. With this, we can monitor the material (with dummy material number) stock with vendor (please note we can see only quantity and not value) . 

12. When we do GR for external purchase order, we receive only the operation performed. (So, conversion cost to vendor shall be paid). 

13. After ensuring GR is done, order confirmation of operation 0020 has to be done. (here we capture the quantity and also the valuation of material in production order).

SAP PP Tips

See also
Production Order Inspection Lot

Get help for your SAP PP Problems
SAP PP Forum - Do you have a SAP PP Question?

SAP Production Planning Books
SAP PP Certification, Interview Questions and Configuration Books

SAP PP Tips
SAP PP Tips and Production Planning/Control Discussion Forum

Best regards,
SAP Basis, ABAP Programming and Other IMG Stuff
http://www.erpgreat.com

All the site contents are Copyright © www.erpgreat.com and the content authors. All rights reserved.
All product names are trademarks of their respective companies.  The site www.erpgreat.com is in no way affiliated with SAP AG.
Every effort is made to ensure the content integrity.  Information used on this site is at your own risk.
 The content on this site may not be reproduced or redistributed without the express written permission of
www.erpgreat.com or the content authors.