The Concept Of MRP In ERP
ERP SAP Modules
==> PP In SAP
The Concept Of MRP in SAP
MRP in brief :
MRP is the planning tool in SAP which will look at all
aspects of a material and is highly based upon the master data of the material.
MRP looks at current inventory, current requirements, open purchase req/orders
and so on. So if a material is required to satisfy a sales order and there
is no inventory, MRP will create a planned order if the item is to be produced
in house. This planned order can then be converted to a production order
by the master scheduler. If the item is to be procured, then MRP will create
a purchase req which the Buyer will convert to a purchase order. This is
just one scenario, the system is highly configurable and will do pretty
much whatever you tell based on config and master data.
Consumption based planning
- Reorder planning
- Forecast based planning
- Time phased planning
Details of re-order planning
Our motive is to maintain optimum stock level of all
the material included in the resource planning. so in this user or system
sets a particular quantity of stock as reorder point . Whenever stock quantity
fall below this point(reorder point) mrp comes into action and generates
procurement proposals according to the settings done in implementation
guide
MRP run procedure
1. Create requirement or demand in MD61
2. MRP run by MD02 for a single material
3. See the result in stock requirement list in MD04.
MRP run we can carry out by
1. MD02 - single item multi level
2 .MD03 - single item single level
3 .MD01 - Total planning
4. MD04 Check MRP
5. MD05 MRP lists
For PP, you require following Master Data
1. Material master (MM01)
Tips: Create
same Material Code in Different Company Codes
2. BOM (CS01)
3. Routing (CA01)
4. Work Center (CR01)
5. CK11N / CK40N - Cost Estimate
Production Cycle: -
1. PIR (Planned Independent Reqmt. - MD61)
2. MD02 - MRP Run
3. MD04 - Stock Requirement List
Tips: MD04
- Inconsistencies after PGI - SDRQCR21
4. CO40 - Convert Planned Orders to Production Order
OR CO01 - Create Production Order
5. Here in Production Order - Schedule Order, Release
order
6. MIGO / MB1A - Goods Issue against Order (Mvmt Type
261)
7. CO11N - Production Operation confirmation
Tips: Add
An Entry Field In CO11n
8. MIGO / MB31 - GR against Prd order
9. CO02 - Technical completion of order
10. KO88 - Order Settlement
Get help for your SAP PP Problems
SAP PP Forum
- Do you have a SAP PP Question?
SAP Production Planning Books
SAP PP
Certification, Interview Questions and Configuration Books
SAP PP Tips
SAP PP Tips and
Production Planning/Control Discussion Forum
Other Logistics Modules
Main Index
SAP Basis, ABAP
Programming and Other IMG Stuff
All the site contents are Copyright © www.erpgreat.com
and the content authors. All rights reserved.
All product names are trademarks of their respective
companies. The site www.erpgreat.com is in no way affiliated with
SAP AG.
Every effort is made to ensure the content integrity.
Information used on this site is at your own risk.
The content on this site may not be reproduced
or redistributed without the express written permission of
www.erpgreat.com or the content authors.
|