We can return the budget in the project via CJ38 Enter the necessary data and choose Return.
The Change Return: WBS Element Overview screen appears. Enter the corresponding data.
Notes: Only the WBS elements where the Budget Return business transaction is allowed are ready for input. To select the timeframe for which you want to enter a return, choose Annual values -> Previous or Next. Enter the returns and choose Continue. Save the returns. Also you can return the budget from the project using CJ35. |