See The Scope of ATP Check
How to see the scope of ATP check?
When we creat a sales order, we can only confirm the delivery
of goods, for the required delivery date if the goods are available for
all the necessary processing activities which take place before delivery.
Types of availability check:
There are 3 types of availability checks in sales document
processing:
1. Check on the basis of ATP quantities (Available To
Promise)
2. Check against Product Allocation
3. Check against planning.
Check on the basis of ATP Quantities
The ATP quantity is calculated from the ware house stock,
The planned inward movements of stocks (purchase orders,
planned orders, production orders, etc) and
The planned out ward movements of stock (Sales orders,
delivery documents, etc.)
This type of check is performed dynamically for each transaction
with or without replenishment lead time (RLT).
RLT : It is the time that is needed to order or
produce the requested material, the system determines the RLT according
to specific times maintained in the material master record. Depending on
the material type RLT can be calculated according to various time periods.
For ex: In the case of trading goods it is determined
according to the planned delivery time, purchase processing time and the
goods receipt processing time.
Availability check including RLT:
Availability is checked up to the end of Replenishment
Lead Time. If the material availability data is calculated on the basis
of current date to lie after the RLT, item it self can be confirmed despite
insufficient stock being available. In this case the system assumes that
any quantity requested by the customer can be procured by the material
availability date and consider the goods to be available.
Controlling availability check in sales document processing.
We need to customize SD Specific settings and General
Settings
General Control Features: The following control elements
need to be maintained in customizing and in the material master record.
1. Strategy group: The allowed planning strategies i.e.
the main strategy and further possible strategies are combined in a strategy
group. It is specified in the Material Master Record in MRP3 view.
Note: In customizing, the strategy groups are assigned
to MRP groups depending on the Plant so that the strategy group is automatically
proposed in the Material Master.
2. MRP group: The MRP group combines the material from
the point of material requirements planning which is specified on the MRP1
view in the Material Master Data.
SD Specific Control Features:
1. Requirements class: It controls all control features
for planning and is also specifies whether the availability check is to
take place for materials in the SD documents on the basis of ATP quantities
and whether the requirements are to be passed on.
SPRO
Sales and distribution
Basic functions
Availability check and transfer of requirements
Availability check
Availability check with ATP planning or against planning
Define procedure by requirement class
Checking groups:
Checking group controls whether the system is to create
individual or collective requirements in sales and shipping process. In
addition a material block for the availability check with transfer of requirements
can be set here. The checking group can also be used to deactivate the
availability check.
SPRO
Sales and distribution
Basic functions
Availability check and transfer of requirements
Availability check
Availability check with ATP planning or against planning
Define checking groups
Checking rule: We use the checking rule to control the
scope of availability check for each transaction the SD process.
Checking rule in the combination of checking group determines
the scope of availability check
Creating checking rule
SPRO
Material management
Purchasing
Purchase order
Set up stock transport order
Create checking rule
Scope of availability check
SPRO
Sales and distribution
Basic functions
Availability check and transfer of requirements
Availability check
Availability check with ATP planning or against planning
Carry out control for availability check
Go to New Entries and define the scope of check in the
combination of checking group and checking rule.
The following elements can be involved in the availability
check
STOCKS:
[]Include safety stocks: Minimum stock at plant/ware
house
[]Stock in transfer
[]Include quality inspection stock
[]Include
Inward movement
Out ward movement
Purchase orders
Sales requirements
Purchase requisitions Deliveries
Planned orders
Release orders etc.
Production orders
If we do not check the field [] ‘check without RLT’ the
system considers RLT while checking the availability of the material
Note: Blocking the material for availability check
SPRO
Sales and distribution
Basic functions
Availability check and transfer of requirements
Availability check
Availability check with ATP planning or against planning
Define material block for other users
If we check the field Block [] during the availability
check of a material the users cannot make changes in the Material Master,
cannot create PO, cannot create sales orders.
Note: During the Material Master creation the system automatically
proposes the checking group. Further the following setting is required.
SPRO
Sales and distribution
Basic functions
Availability check and transfer of requirements
Availability check
Availability check with ATP planning or against planning
Define checking groups default values.
We need to assign the checking group to the combination
of material type and plant.
Get help for your SAP SD problems
SAP SD Forums - Do you
have a SAP SD Question?
SAP Sales and Distribution Books
SAP
SD Books - Certification, Interview Questions and Configuration
Delivery Hints
SAP Logistics Execution
SAP Sales and Distribution Tips
SAP SD Discussion Forum and Sales/Distribution
Tips
Best regards,
SAP Basis, ABAP Programming and Other IMG Stuff
http://www.erpgreat.com
All the site contents are Copyright © www.erpgreat.com
and the content authors. All rights reserved.
All product names are trademarks of their respective
companies. The site www.erpgreat.com is in no way affiliated with
SAP AG.
Every effort is made to ensure the content integrity.
Information used on this site is at your own risk.
The content on this site may not be reproduced
or redistributed without the express written permission of
www.erpgreat.com or the content authors.
|