Billing Plan for Milestone Billing

Milestone billing means distributing the total amount to be billed over multiple billing 
dates in the billing plan. 

As each milestone is successfully reached, the customer is billed either a percentage of 
the entire project cost or simply a pre-defined amount.

During sales order processing, the system determines from the item category whether a 
billing plan is required and, if so, which type of plan

The type of billing plan that is determined at this point is set up in Customizing and 
cannot be changed in the sales document. 

Billing plans for periodic billing and milestone billing plans for project-related milestone 
billing have different overview screens so that you can enter data relevant to your 
processing. 

For example, for milestone billing, you must be able to enter data to identify the 
individual milestones.


IMG configuration requires :-

1.  Maintain billing plan types for milestone billing in OVBO.

2.  Define date description in SM30 - V_TVTB.

3.  Maintain Date Category for Billing Plan Type IN OVBJ.

4.  Allocate date category in SM30 - V_TFPLA_TY.

5.  Maintain date proposal for Billing Plan Type in OVBM.

6.  Assign Billing Plan Type to Sales Documents Type in OVBP.

7.  Assign Billing Plan Type to Item Categories in OVBR.

8.  Define rules for determining the date in OVBS.


Milestone billing is typically used for billing projects, such as plant engineering and 
construction projects. Such projects often include a series of milestones that mark the 
completion of different stages of the work. In the SAP R/3 System, milestones are defined 
in a network along with planned and actual dates for the completion of work. The milestones 
are also assigned to the billing dates in the billing plan. 


Each milestone-related billing date is blocked for processing until the Project System 
confirms that the milestone is completed.


Delivery-relevant order items for which a milestone billing plan applies are billed on the 
basis of the requested delivery quantity and not on the total of the confirmed quantities.

 
The connection between the project and the sales document item is made in the individual 
schedule lines of the item. Each schedule item can be assigned to a network in a project.

To display the project-related data for a schedule line, proceed as follows:

In one of the overview screens of the sales document, select 

1.  Item -> Schedule lines.
2.  Mark the schedule line and select Procurement details.

 
The following figure shows an example of milestone billing where only the Contract have
been billed :

Order  Item  Turbine    100,000

Billing Plan

Billing date Description    %  Value  Billing Block   Milestone   Billing Status
01-10-94     Contract      10  10,000      -             x           x  
01-03-95     Assembly      30  30,000      x             x           
01-04-95     Maintenance   30  30,000      x             x
01-05-95     Acceptance    30  30,000      x             x
01-06-95     Final invoice ..    ..        x

Network/Activities

Milestone    Estimate      Actual
Assembly     01-03-95      01-03-95
Maintenance  01-04-95      
Acceptance   01-05-95

For each billing date in a milestone billing plan, you can specify whether the billing 
date is:

1.  fixed 
2.  always updated with the actual date of the milestone 
3.  updated with the actual date of the milestone, if the date is earlier than the 
    planned billing date for the date 

Related Topics:
Create/Modify Billing Document Type
Steps for creating new or changing existing Billing Doc Type

SAP SD Books
SAP Sales and Distribution, Certification, Interview Questions Reference Books

SAP Sales and Distribution Tips
SAP SD - Sales/Distribution Tips

Best regards,
SAP Basis, ABAP Programming and Other IMG Stuff
http://www.erpgreat.com

All the site contents are Copyright © www.erpgreat.com and the content authors. All rights reserved.
All product names are trademarks of their respective companies.  The site www.erpgreat.com is in no way affiliated with SAP AG. 
Every effort is made to ensure the content integrity.  Information used on this site is at your own risk. 
 The content on this site may not be reproduced or redistributed without the express written permission of 
www.erpgreat.com or the content authors.